NCDRC orders Hero Realty to pay Mohali homebuyers 10.4% delay compensation
The National Consumer Disputes Redressal Commission has ordered Hero Realty to pay Hero Homes Mohali buyers 10.4% a year for late possession and dropped green-area location charges in four cases.
Key points
- The National Consumer Disputes Redressal Commission partly allowed appeals over the Hero Homes project in Mohali on 18 November 2026.
- Buyers get delay compensation at 10.4% a year simple interest from 30 June 2022 to 4 September 2023, the occupancy certificate date.
- The commission held that signing a conveyance deed does not end a buyer's claim for earlier deficiency in service; the order may be appealed.

Photo: Blogtrepreneur / Wikimedia Commons, CC BY 2.0 (cropped). Representational image.
The National Consumer Disputes Redressal Commission has ordered Hero Realty Private Limited to pay homebuyers of its Hero Homes project in Sector 88, SAS Nagar (Mohali), delay compensation at 10.4% a year for late possession. The commission pronounced the order on 18 November 2026, deciding a batch of appeals by the builder and cross appeals by flat buyers against orders of the Punjab State Consumer Disputes Redressal Commission dated 14 October 2025 and 28 October 2025.
What Happened
The commission partly allowed the appeals. It held that the homebuyers are entitled to delay compensation at 10.4% a year simple interest from 30 June 2022 to 4 September 2023, the date of the occupancy certificate. Where possession was offered after that date, compensation runs until the offer of possession. Any delay compensation already received is to be adjusted.
The compensation is payable on amounts paid towards the sale price up to 30 June 2022, and on later payments from the date each was made. It is not payable on taxes or GST, provided the builder deposited them with the authorities within one month of receiving them; otherwise it is payable on those sums too for the period of delay.
The Rs 35,000 the State Commission had awarded in each case for mental agony, harassment and litigation cost was replaced with litigation cost of Rs 10,000 per case. In four cross appeals, the commission held that the builder showed a basketball ground separately from the green area in its brochure but later built it in the green area, which it called a deficiency in service, and ruled that the preferential location charges for that green area are not payable.
What It Means
The commission rejected the builder's argument that buyers who had signed conveyance deeds had no remaining claim. Relying on a 2026 Supreme Court ruling, it held that taking possession or signing the conveyance deed does not end a buyer's right to claim for deficiency in service before that date. It also upheld the State Commission's finding that the buyers are consumers under the Consumer Protection Act. The order may be appealed. Homebuyers can approach the National Consumer Helpline on 1915 or file through e-Daakhil.
Source: Consumer commission order
Sources & Citations
- Consumer commission order — Consumer commission