NCLAT stays insolvency process against ESPO Developers in Omkara ARC case
The NCLAT has stayed the insolvency process of ESPO Developers that the NCLT started on Omkara Assets Reconstruction's plea, saying the debt and default are not free from substantial doubt.
Key points
- The NCLAT on 25 November 2026 stayed the insolvency process of ESPO Developers until its next order.
- The NCLT had admitted Omkara Assets Reconstruction's insolvency plea against the company on 29 September 2026.
- The NCLAT said its view is only prima facie; the arbitration between the parties continues, and its order may be appealed.

Photo: Breather breather / Wikimedia Commons, CC0 1.0 (cropped). Representational image.
The National Company Law Appellate Tribunal (NCLAT) has stayed the corporate insolvency resolution process of ESPO Developers Private Limited until its next order. In an interim order of 25 November 2026, its Principal Bench in New Delhi said the existence of the debt and the default claimed by the lender, Omkara Assets Reconstruction Private Limited, were not free from substantial doubt.
What Happened
The New Delhi bench of the National Company Law Tribunal (NCLT) had admitted Omkara Assets Reconstruction's application under Section 7 of the Insolvency and Bankruptcy Code on 29 September 2026. A suspended director of the company appealed.
According to the order, the lender says Rs 135.15 crore was disbursed under a loan agreement of 18 January 2019. A one-time settlement followed in 2021, and a settlement agreement on 29 March 2023 combined the loan liability with obligations under an agreement to sell property inventory. The lender terminated that settlement on 11 July 2024 and says the original loan revived. The company disputes the termination, and the parties have been in arbitration since late 2024, where the lender has filed a counter-claim.
The NCLAT held that insolvency proceedings are not a substitute for deciding disputed contract claims or a means of recovery. It said the claimed revival of the loan depends largely on whether the termination was valid, which is itself before the arbitral tribunal. It found that the company could suffer harm that might not be undone if the process went ahead, while the lender can pursue its counter-claim in arbitration.
What It Means
Further steps in the company's insolvency process are on hold until the NCLAT's next order. The arbitration continues, and the lender remains free to pursue its remedies there. The NCLAT said its observations are prima facie and confined to interim relief, and are not findings on the parties' final rights. The appeals will be heard further once pleadings are complete. An NCLAT order may be appealed to the Supreme Court.
Source: NCLAT order
Sources & Citations
- NCLAT order — National Company Law Appellate Tribunal