Maharashtra consumer commission orders Prajapati Developers to pay delay interest to homebuyer

The Maharashtra State Consumer Disputes Redressal Commission held Prajapati Developers deficient in service for delaying a Navi Mumbai flat and ordered 10% interest on Rs 57.27 lakh.

Key points

  • The Maharashtra State Consumer Disputes Redressal Commission held on 18 November 2026 that Prajapati Developers was deficient in service.
  • The developer must hand over the flat with the occupation certificate within 45 days and pay 10% a year interest on Rs 57,27,734 from 30 June 2021.
  • The commission held that MahaRERA timeline extensions do not by themselves take away a buyer's right to delay interest; the order may be appealed.
Oquilia Newsroom
Financial news desk covering SEBI, RBI, IRDAI, and Budget-related developments.
2 min read · 381 wordsहिन्दी में पढ़ें
Verified SourcesSource: Consumer commission
Timeline of a delayed flat in the Prajapati Magnum project: agreement on 22 December 2017, possession promised by 30 June 2021, part occupation certificate on 26 April 2023, work pending at inspection on 30 April 2023, and the order of 18 November 2026 for 10% interest on Rs 57,27,734.
Oquilia graphic. Source: Maharashtra State Consumer Commission order, 18 November 2026

The Maharashtra State Consumer Disputes Redressal Commission has held Prajapati Developers, a partnership firm, and its partners deficient in service for failing to deliver a flat in its "Prajapati Magnum" project at Dronagiri, Navi Mumbai, on time. In an order dated 18 November 2026, the commission directed them to hand over the flat and pay a homebuyer interest at 10% a year on Rs 57,27,734 from 30 June 2021.

What Happened

According to the order, the homebuyer booked a 43.3 square metre flat for Rs 59 lakh under an agreement for sale registered on 22 December 2017, and paid Rs 57,27,734 including taxes, partly with a home loan. The agreement promised possession by 30 June 2021. The developer obtained a part occupation certificate only on 26 April 2023, and on inspection on 30 April 2023 its site representative recorded that work in the flat was pending, the commission noted.

The developer argued that the delay was caused by litigation over CIDCO's development rules, Airport Authority of India height clearances and other regulatory hurdles, and that MahaRERA had extended its timeline to June 2023. The commission held that such general hurdles cannot be a "perpetual shield" without a direct, site-specific link to the project, and that timeline extensions by MahaRERA do not by themselves take away a buyer's right to delay interest.

The commission directed the developer and its partners, jointly and severally, to hand over the completed flat with the occupation certificate within 45 days, subject to the homebuyer paying any undisputed balance and legitimate maintenance and statutory charges. They must also pay interest at 10% a year on Rs 57,27,734 from 30 June 2021 until possession, Rs 1 lakh as compensation for mental agony and Rs 50,000 as litigation costs. The homebuyer had sought interest at 15.45% a year and Rs 5 lakh in compensation.

What It Means

For homebuyers facing delayed possession, the order is a reminder that a developer's regulatory troubles or a registration extension do not automatically cancel the buyer's claim for delay interest. The commission also said a buyer must clear their own dues under the agreement. The order may be appealed. Homebuyers with similar grievances can approach the National Consumer Helpline on 1915 or file a complaint online through e-Daakhil.

Source: Consumer commission order