ED attaches Rs 702.70 crore properties in Ozone Group homebuyers case in Bengaluru

The ED's Bengaluru office has provisionally attached flats and land worth Rs 702.70 crore in its probe into Ozone Group entities, which it alleges did not deliver apartments booked by homebuyers.

Key points

  • The ED's Bengaluru zonal office provisionally attached flats and land worth Rs 702.70 crore under the PMLA on 25 November 2026.
  • The ED alleges Ozone Group entities collected about Rs 1,305.11 crore from homebuyers without delivering the booked units.
  • This adds to Rs 423.37 crore attached in October 2025; the attachment must be confirmed by the PMLA Adjudicating Authority.
Oquilia Newsroom
Financial news desk covering SEBI, RBI, IRDAI, and Budget-related developments.
2 min read · 370 wordsहिन्दी में पढ़ें
Verified SourcesSource: Enforcement Directorate
Enforcement / 26 Nov 2026 / Enforcement Directorate

The Enforcement Directorate (ED) has provisionally attached flats and land worth Rs 702.70 crore in its money-laundering case against Ozone Urbana Infra Developers Pvt. Ltd. and others, the agency said on 26 November 2026. The ED's Bengaluru zonal office issued the attachment order, numbered 45 of 2026, on 25 November 2026 under the Prevention of Money Laundering Act (PMLA), 2002.

What Happened

The ED's case is based on several FIRs for cheating and criminal conspiracy under the Indian Penal Code, registered by the Karnataka Police and by the CBI's Economic Offences Wing-I, New Delhi, on the directions of the Supreme Court. The FIRs allege that residential projects were not completed, booked apartments were not delivered and money collected from homebuyers was not refunded.

According to the ED, Ozone Group entities persuaded homebuyers to book units through subvention, buyback and zero-down-payment schemes, with promises that the builder would pay the buyers' pre-EMIs or EMIs until possession. The ED alleges that five group companies, for the Aqua-2, Avenue, Prime, Metrozone, WF-48 and Polestar projects, along with the group's chairman and managing director, cheated homebuyers of about Rs 1,305.11 crore and did not hand over the units.

The ED said housing loans were paid directly to the builder entities, but the projects stayed incomplete. It alleges the money was moved between group companies through inter-corporate deposits and used to repay loans, interest, investors and corporate expenses instead of construction. Properties worth Rs 423.37 crore were attached earlier, by an order dated 4 October 2025. Further investigation is in progress.

What It Means

A provisional attachment stops the properties from being sold or transferred while the case goes on. It must be confirmed by the Adjudicating Authority under the PMLA. These are allegations, not findings of guilt; the accused are presumed innocent until proven guilty in court, and due process continues.

For homebuyers in these projects, the attached properties are held while the case continues. The ED's account shows how buyers were drawn in by promises that the builder would pay their EMIs until possession. Homebuyers with a complaint against a builder can file a consumer complaint through the National Consumer Helpline (1915) or e-Daakhil.

Source: Enforcement Directorate press release

This report describes enforcement actions and allegations on the public record, attributed to the officials cited. An order, FIR or chargesheet is not a conviction; parties are presumed innocent until proven guilty.

Named in this report, or spotted an error? Corrections and responses: editor@oquilia.com. We correct errors promptly and record responses from named parties.

Sources & Citations

  1. Enforcement Directorate press release — Enforcement Directorate

This article was last reviewed on 26 November 2026 by Oquilia's editorial team. Every claim is sourced from primary regulatory materials (CBDT, IRDAI, RBI, SEBI, Indian Kanoon). View our methodology.

Found an error? Report an issue.