K-REAT upholds agreed price for Bengaluru penthouse buyer, drops delay interest

The Karnataka Real Estate Appellate Tribunal held that BVL Estates must sell a penthouse at the originally agreed rate, but set aside the delay-period interest K-RERA had awarded.

Key points

  • The Karnataka Real Estate Appellate Tribunal partly allowed BVL Estates' appeal against a K-RERA order on 17 November 2026.
  • The tribunal confirmed the agreed sale price of Rs 1,74,94,260 and set aside the K-RERA award of Rs 11,22,868 as delay interest.
  • The builder must sign the agreement for sale within 15 days and hand over possession within 60 days once the balance is paid.
Oquilia Newsroom
Financial news desk covering SEBI, RBI, IRDAI, and Budget-related developments.
2 min read · 352 wordsहिन्दी में पढ़ें
Verified SourcesSource: Karnataka Real Estate Appellate Tribunal
Rows of old bound law reports on a dark shelf

Photo: Dominic / Wikimedia Commons, CC0 1.0 (cropped). Representational image.

The Karnataka Real Estate Appellate Tribunal (K-REAT) on 17 November 2026 held that BVL Estates Private Limited must sell a penthouse in its Bengaluru project 'Krishvi BVL Statura' to a homebuyer at the originally agreed price of Rs 1,74,94,260. It partly allowed the builder's appeal, setting aside the delay-period interest that the Karnataka Real Estate Regulatory Authority (K-RERA) had awarded on 26 December 2025.

What Happened

According to the judgment, the homebuyer, who is also a director of the builder company, booked penthouse No. 3303 and later complained that the builder demanded an enhanced rate of Rs 10,000 per square foot without signing an agreement for sale. K-RERA had ordered the builder to honour the original rate, pay Rs 11,22,868 as interest for delay, and hand over possession.

The builder argued that a director could not complain against his own company. The tribunal rejected this, holding that a company is a separate legal entity and that a director, in his individual capacity, keeps the rights of an allottee under the RERA Act. It held that the builder could not raise the price on its own without the buyer's consent, and confirmed the original rate of Rs 3,569 per square foot. It set aside the interest award, noting that the original complaint had not sought it.

The tribunal ordered the builder to sign the agreement for sale within 15 days. The buyer must pay the balance of Rs 1,19,94,260 within 30 days. The builder must then register the sale deed, obtain an occupancy certificate and hand over possession within 60 days of the order. If it fails, the buyer is entitled to interest at SBI MCLR plus 2% a year on the full price.

What It Means

The ruling says that a price agreed in an allotment letter and draft agreement binds the builder, even before an agreement for sale is signed, and that a builder cannot raise it unilaterally. It also shows that a relief such as delay interest should be sought in the complaint itself. A K-REAT judgment may be appealed to the High Court.

Source: K-REAT judgment

Sources & Citations

  1. K-REAT judgment — Karnataka Real Estate Appellate Tribunal

This article was last reviewed on 18 November 2026 by Oquilia's editorial team. Every claim is sourced from primary regulatory materials (CBDT, IRDAI, RBI, SEBI, Indian Kanoon). View our methodology.

Found an error? Report an issue.